About

Origin of the National Medical Equipment Database project

  • Origin of the National Medical Equipment Database project goes back to 2015 – from the Scottish Assets and Facilities Report (SAFR) Technical Expert Group.
  • Picked up under the Shared Services Agenda in 2016 as a Once for Scotland initiative.
  • Final business case produced in May 2019.
  • There was broad support but funding was not secured so the project was held in abeyance.

March 2020 and Covid-19

  • The Covid-19 virus came to the United Kingdom and national lockdown started on March 2020.
  • Suddenly there was intense interest in what medical equipment we had, how much we had and where it was across the country.
  • Data was gathered manually from the health boards on key medical equipment, collated into spreadsheets, cleansed and harmonised to made workable.
  • The process could take days instead of the minutes that it could have – if only there was a National Database!
  • A revised business case was developed in collaboration with a parallel work-stream around capital replacement of Imaging / High-End Equipment
  • Presented to the National Infrastructure Board
  • Funding agreed

Data saves lives: reshaping health and social care with data

  • When facing the greatest public health emergency that this country has tackled for generations, one of the most impactful tools at our disposal was the power of data.
  • Deliver better treatment for patients, better health results for people who need care and support, and better decision making, research, and support for our colleagues on the front line.
  • Harnessing data to improve patient and service user safety.
  • Staff can only do their best when they have the right information, so staff will have easy access to the right information to provide the best possible care.
  • Modernising our data architecture
  • Promoting and developing data and technical standards.

NHS Scotland’s National Infrastructure Board
Terms of Reference, 2021

  • The National Infrastructure Board will have the authority to mandate action (and oversee compliance) from NHS Boards on any national information requests, and/or any remedial or improvement works it deems necessary.
  • It will determine national priorities for infrastructure change and investment, maintenance of the retained estate, and disposal of redundant estate.

Project Numbers

  • Agreed funding of £324k for the project from the NIB
  • Additional funding of £83k to cleanse and data transformation – details coming up (Medical Devices and Legislation Unit)

Timelines

  • Data provided by all Health Boards by 5/11/21
  • Training local Health Board staff on new fields GMDN, GTINs, etc. in Jan/ Feb 2022
  • Data cleansing and transformation by Feb 2022
  • Tender started before Christmas
  • Supplier identified late summer
  • Transition to the national database complete in financial year 22/23

Input needed from Health Boards – current/ past

  • Membership of the Project Board and Sub Groups for Nomenclature & Governance
  • Membership short life working groups e.g. Role Access, Weighting & Scoring 
  • General advice and support
  • Providing data for piloting transformation

Initially Serial number/ Brand/ Model/ Category/ Purchase Date

Plus any codes we intend to add GMDN, EMDN, UNSPSC, UDI DI, manufacturer’s part code

  • Returning data
  • Training for Health Boards
  • Transition
  • System capabilities
  • Discussion

Legacy data

Size of the current database

  • All data – Outlier data e.g. patient information

When you require record patient data

What medical conditions

Volume of occasions e.g. 100 patients, or 10% of the population etc

Input from Health Boards needed – future

  • Transition planning
  • Data Analysts
  • Where possible, uploading data to current systems with extra fields
  • Training staff in coding and classifications
  • Identifying all current roles from the access

Meetings

General up to now

  • Capital & Infrastructure Network
  • UDI Programme Board
  • Scottish Health Technologies Group
  • National Infrastructure Board – Equipment Group

Next Stage

  • Series of quarterly meetings to update Health Boards on progress
  • Local meetings – with Health Boards and others you feel need to be involved in the local implementation (probably 4-5 in each Health Board area) e.g. could be a Facilities Director, or someone from your planning department or IT department.